The Chronicle -

By Verlean McCoy
President, Creswell Heritage Foundation 

Old Schoolhouse update: Foundation, porch replacement report

 

June 20, 2019



Creswell Heritage Foundation board members and volunteers are currently completing site work at Old Schoolhouse, but the Foundation and Porch Replacement Project is otherwise complete. We want to share some of the details of how this was made possible.

The project cost $107,116.65 in contractor and architect fees. Of this, $69,000 was covered by eight grants: $25,000 from the Oregon Community Foundation Fred W. Fields Fund; $20,000 from Oregon Parks and Recreation’s Preserving Oregon Fund; $10,000 and another $2,500 from the Kinsman Foundation; $5,000 from the Chambers Family Foundation;...



For access to this article please sign in or subscribe.



 
 